BVW#7 Compressor Station Project
The BVW#7 Compressor Station Project defines the erection of a compressor station to increase the capacity of the existing Yadana Gas Pipeline System (42”, 238 Km total length, 12 block valve stations, metering stations and pigging facilities).
The Compressor Station will mainly consist of inlet filter separators, fuel gas system, gas coolers, station piping, utility systems, buildings and shelters.
It will be equipped with all instruments and controls required for local operation and potential remote control operation in future as well.
DORSCH CONSULT has performed a Conceptual Study to define the basis conditions of the Yadana Gas Pipeline System and subsequently won the ITB for Consultancy Services concerning the erection of the compressor station.
Disciplines
- Oil & Gas
Companies
Dorsch Consult asia Co., Ltd.
Client
PTT Public Company Limited, Thailand
Duration
From 2003 to 2006
Location
Kanchanaburi, Thailand
Project Activities
- Hydraulic simulation and analysis of existing pipeline system
- Soil Survey
- Front End Engineering Design (FEED)
- Safety, health and environment (SH&E) analysis
- Tender Engineering
- Procurement
- Project Management
- Quality Management
- Design Supervision
- Construction Supervision